We represented an international construction joint venture in its administrative disputes with the Railways Authority in connection with the € 370 mil. rehabilitation works carried out at a component of the Pan European Corridor railway under a FIDIC Red Book contract.

 

During the court proceedings held in front of the various Romanian Courts including the High Court of Cassation and Justice there were addressed disputes dealing with the following contractual subject-matters: insufficient expropriations, late giving of the right of access to the site to the Contractor, late handed-over of parts of the technical project by the Employer, occurence of various unforeseeable events that delayed the execution of works.